What does early time represent in project management?
What does early time represent in project management?
Earliest possible moment an event can occur
What does late time represent?
What does late time represent?
Latest moment without causing project delays
Which direction does the forward pass method work?
Which direction does the forward pass method work?
From start to finish
What value do we take when multiple activities converge at a node during forward pass?
What value do we take when multiple activities converge at a node during forward pass?
Largest early time
What is the early time at the source node?
What is the early time at the source node?
0
Which direction does the backward pass work?
Which direction does the backward pass work?
Backwards from end
What value do we take when multiple activities diverge from a node during backward pass?
What value do we take when multiple activities diverge from a node during backward pass?
Smallest late time
What is the formula for total float?
What is the formula for total float?
What defines a critical activity?
What defines a critical activity?
Activity with zero float
What is a critical path?
What is a critical path?
Continuous sequence of critical activities
What does the critical path determine?
What does the critical path determine?
Minimum project duration
What happens at the sink node regarding early and late times?
What happens at the sink node regarding early and late times?
Late time equals early time