Critical Path Analysis (HSC SSCE Mathematics Standard): Flashcards
📚Flashcards
Practise the cards
10 cards from this deck
ShowHide
Practise the cards
10 cards from this deck
Float time (slack time)
Float time (slack time)
Time an activity can delay without affecting project completion
Float time formula
Float time formula
EST stands for
EST stands for
Earliest Start Time
LST stands for
LST stands for
Latest Start Time
Float time of a critical activity
Float time of a critical activity
Zero
Critical path
Critical path
Sequence of critical activities from start to finish
Forward scanning calculates
Forward scanning calculates
EST values
Backward scanning calculates
Backward scanning calculates
LST values
Multiple predecessors: which EST?
Multiple predecessors: which EST?
Largest EST
Multiple successors: which LST?
Multiple successors: which LST?
Smallest LST