Critical Path Analysis (HSC SSCE Mathematics Standard): Flashcards

📚Flashcards
Float Times and the Critical Path
Sign up to keep revising.Create a free account to study more flashcards and track your progress.

Practise the cards

10 cards from this deck

Show

Float time (slack time)

Time an activity can delay without affecting project completion

Float time formula

extFloattime=extLSTextEST ext{Float time} = ext{LST} - ext{EST}

EST stands for

Earliest Start Time

LST stands for

Latest Start Time

Float time of a critical activity

Zero

Critical path

Sequence of critical activities from start to finish

Forward scanning calculates

EST values

Backward scanning calculates

LST values

Multiple predecessors: which EST?

Largest EST

Multiple successors: which LST?

Smallest LST