In a network diagram, how are activities represented?
In a network diagram, how are activities represented?
As labelled arrows (edges)
What does the '—' symbol indicate in an activity chart?
What does the '—' symbol indicate in an activity chart?
Activity has no immediate predecessors
What is an immediate predecessor?
What is an immediate predecessor?
Activity that must finish before another
Which activities connect to the start vertex?
Which activities connect to the start vertex?
Activities with no immediate predecessors
Which activities lead to the finish vertex?
Which activities lead to the finish vertex?
Not immediate predecessors for any other
What is the forward construction method?
What is the forward construction method?
Building from start vertex to finish
When is the backward construction method particularly helpful?
When is the backward construction method particularly helpful?
When multiple paths converge at end
What does 'branching' mean in network diagrams?
What does 'branching' mean in network diagrams?
Multiple activities share same predecessor
What does 'converging' mean in network diagrams?
What does 'converging' mean in network diagrams?
Multiple activities are predecessors for one
A network diagram displays activities, time needed, and what else?
A network diagram displays activities, time needed, and what else?
How activities relate to each other