Introduction to Critical Path Analysis (HSC SSCE Mathematics Standard): Flashcards

📚Flashcards
Introduction to Critical Path Analysis
Sign up to keep revising.Create a free account to study more flashcards and track your progress.

Practise the cards

10 cards from this deck

Show

Critical path analysis

Project management technique for planning complex tasks

Activity chart (also called)

Precedence table

Four columns of activity chart

Activity, Task, Duration, Immediate predecessors

Immediate predecessor

Activity that must finish before another can start

Dash (–) in predecessors column means

No predecessors; activity can start immediately

Multiple immediate predecessors rule

ALL must be completed before next activity can begin

Scheduling in project management

Process of allocating time to complete activities

Activities with no immediate predecessors

Can start immediately without waiting for others

Total duration vs project completion time

Different concepts; parallel activities affect completion time

Critical path analysis helps predict

Whether the project will finish on time