Activity network
Activity network
Visual tool showing task dependencies & relationships
Purpose of activity networks
Purpose of activity networks
Find shortest possible time to complete project
Precedence table
Precedence table
Shows activities, durations, & dependencies
Activity node's 3 sections
Activity node's 3 sections
Earliest start (L), duration (C), latest finish (R)
Forward pass calculates
Forward pass calculates
Earliest start times
Forward pass direction
Forward pass direction
Left to right through network
Earliest start time rule
Earliest start time rule
Maximum of preceding finish times
Backward pass calculates
Backward pass calculates
Latest finish times
Backward pass direction
Backward pass direction
Right to left through network
Latest finish time rule
Latest finish time rule
Minimum of following start times