What does a resource refer to in project management?
What does a resource refer to in project management?
The workforce required to complete a project
What does a resource histogram display?
What does a resource histogram display?
Number of workers needed at each point
What are the axes of a resource histogram?
What are the axes of a resource histogram?
Time (horizontal) and workers (vertical)
What does the height of each bar in a resource histogram indicate?
What does the height of each bar in a resource histogram indicate?
Total workforce requirement for that time
What is resource levelling?
What is resource levelling?
Rescheduling activities within float
What does float represent?
What does float represent?
How much an activity can be delayed
How much float do activities on the critical path have?
How much float do activities on the critical path have?
Zero float
Which activities can be delayed without extending the project?
Which activities can be delayed without extending the project?
Activities not on the critical path
What happens when a critical activity is delayed?
What happens when a critical activity is delayed?
The project duration is extended
How do you construct a resource histogram from a Gantt chart?
How do you construct a resource histogram from a Gantt chart?
Count simultaneous activities and sum workers