Critical Path Analysis 2 (AQA A-Level Further Maths): Quizzes

📚Quizzes
Resourcing
Sign up to keep practising.Create a free account to play more quizzes and track your progress.

Practise the questions

10 questions from this quiz

Show

What does a resource refer to in project management?

The workforce required to complete a project

What does a resource histogram display?

Number of workers needed at each point

What are the axes of a resource histogram?

Time (horizontal) and workers (vertical)

What does the height of each bar in a resource histogram indicate?

Total workforce requirement for that time

What is resource levelling?

Rescheduling activities within float

What does float represent?

How much an activity can be delayed

How much float do activities on the critical path have?

Zero float

Which activities can be delayed without extending the project?

Activities not on the critical path

What happens when a critical activity is delayed?

The project duration is extended

How do you construct a resource histogram from a Gantt chart?

Count simultaneous activities and sum workers