Critical Path Analysis 1 (AQA A-Level Further Maths): Quizzes
📚Quizzes
Practise the questions
10 questions from this quiz
ShowHide
Practise the questions
10 questions from this quiz
What is the main purpose of an activity network?
What is the main purpose of an activity network?
To show shortest possible project time
What 3 pieces of info are needed to create a project timetable?
What 3 pieces of info are needed to create a project timetable?
Activities list, dependencies, duration
What are the 3 columns in a precedence table?
What are the 3 columns in a precedence table?
Activity, Duration, Depends on
What goes in the LEFT section of an activity node?
What goes in the LEFT section of an activity node?
Earliest start time
In which direction do you work when doing a forward pass?
In which direction do you work when doing a forward pass?
Left to right
When calculating earliest start time, do you take max or min of preceding finish times?
When calculating earliest start time, do you take max or min of preceding finish times?
Maximum
What does a backward pass calculate?
What does a backward pass calculate?
Latest finish times
When calculating latest finish time, do you take max or min of following start times?
When calculating latest finish time, do you take max or min of following start times?
Minimum
How is the project duration found?
How is the project duration found?
Complete forward pass to End node
What is a common error when doing a forward pass?
What is a common error when doing a forward pass?
Taking minimum instead of maximum
