Critical Path Analysis 1 (AQA A-Level Further Maths): Quizzes

📚Quizzes
Activity Networks
Sign up to keep practising.Create a free account to play more quizzes and track your progress.

Practise the questions

10 questions from this quiz

Show

What is the main purpose of an activity network?

To show shortest possible project time

What 3 pieces of info are needed to create a project timetable?

Activities list, dependencies, duration

What are the 3 columns in a precedence table?

Activity, Duration, Depends on

What goes in the LEFT section of an activity node?

Earliest start time

In which direction do you work when doing a forward pass?

Left to right

When calculating earliest start time, do you take max or min of preceding finish times?

Maximum

What does a backward pass calculate?

Latest finish times

When calculating latest finish time, do you take max or min of following start times?

Minimum

How is the project duration found?

Complete forward pass to End node

What is a common error when doing a forward pass?

Taking minimum instead of maximum

Join 100,000+ A-Level students studying Quizzes with us.

Select your subjects, and get access to A+ resources today.