Activity network

Visual tool showing task dependencies & relationships

Purpose of activity networks

Find shortest possible time to complete project

Precedence table

Shows activities, durations, & dependencies

Activity node's 3 sections

Earliest start (L), duration (C), latest finish (R)

Forward pass calculates

Earliest start times

Forward pass direction

Left to right through network

Earliest start time rule

Maximum of preceding finish times

Backward pass calculates

Latest finish times

Backward pass direction

Right to left through network

Latest finish time rule

Minimum of following start times