Critical Path Analysis 2 (AQA A-Level Further Maths): Flashcards
📚Flashcards
Practise the cards
10 cards from this deck
ShowHide
Practise the cards
10 cards from this deck
Resource in project mgmt
Resource in project mgmt
Workforce required to complete a project
Resource histogram
Resource histogram
Bar chart showing number of workers needed over time
Resource levelling
Resource levelling
Technique to reduce max workers by rescheduling activities
Float
Float
Flexibility in activity timing without affecting completion
Resource histogram axes
Resource histogram axes
Horizontal: time; Vertical: number of workers
Float for critical path activities
Float for critical path activities
Zero float
Effect of delaying critical activity
Effect of delaying critical activity
Extends the project duration
What resource levelling uses
What resource levelling uses
Float of non-critical activities
When workers available < peak requirement
When workers available < peak requirement
Project must be extended by delaying critical activities
Height of resource histogram bar
Height of resource histogram bar
Total workforce requirement for that time period