Minimum Completion Time (HSC SSCE Mathematics Standard): Flashcards

📚Flashcards
Minimum Completion Time
Sign up to keep revising.Create a free account to study more flashcards and track your progress.

Practise the cards

10 cards from this deck

Show

Minimum completion time definition

Shortest time to finish entire project

How to find minimum completion time from network diagram

EST value at finish node

Crashing definition

Reducing activity duration to speed up project

Which activities reduce completion time when crashed

Only activities on critical path

Formula for float time

Float time=LSTEST\text{Float time} = \text{LST} - \text{EST}

What zero float time indicates

Activity is on the critical path

What non-critical activities have

Float time available

Effect of crashing non-critical activities individually

Does not reduce overall project completion time

What can happen to critical path after crashing activities

Critical path can change to different route

How to identify critical path

Find activities with zero float time

Join 100,000+ SSCE students studying Flashcards with us.

Select your subjects, and get access to A+ resources today.