10 questions from this quiz
EST at the finish node
Reducing activity duration & recalculating
Only activities on the critical path
It is on the critical path
Float time=LST−EST\text{Float time} = \text{LST} - \text{EST}Float time=LST−EST
They have float time available
The critical path can change
Duration of activities & their order
It can take longer without delaying project
Recalculate all EST and LST values