What does the minimum completion time equal in a network diagram?
What does the minimum completion time equal in a network diagram?
EST at the finish node
What is crashing in project management?
What is crashing in project management?
Reducing activity duration & recalculating
Which activities should be crashed to reduce overall project completion time?
Which activities should be crashed to reduce overall project completion time?
Only activities on the critical path
What does zero float time indicate about an activity?
What does zero float time indicate about an activity?
It is on the critical path
How is float time calculated?
How is float time calculated?
Why won't reducing non-critical activities speed up the project overall?
Why won't reducing non-critical activities speed up the project overall?
They have float time available
What can happen to the critical path after crashing activities?
What can happen to the critical path after crashing activities?
The critical path can change
What two factors determine the minimum completion time?
What two factors determine the minimum completion time?
Duration of activities & their order
What does it mean if an activity has float time?
What does it mean if an activity has float time?
It can take longer without delaying project
What must be done after crashing activities in a network diagram?
What must be done after crashing activities in a network diagram?
Recalculate all EST and LST values