Constructing a Network Diagram Given an Activity Chart
Sign up to keep practising.Create a free account to play more quizzes and track your progress.

Practise the questions

10 questions from this quiz

Show

In a network diagram, how are activities represented?

As labelled arrows (edges)

What does the '—' symbol indicate in an activity chart?

Activity has no immediate predecessors

What is an immediate predecessor?

Activity that must finish before another

Which activities connect to the start vertex?

Activities with no immediate predecessors

Which activities lead to the finish vertex?

Not immediate predecessors for any other

What is the forward construction method?

Building from start vertex to finish

When is the backward construction method particularly helpful?

When multiple paths converge at end

What does 'branching' mean in network diagrams?

Multiple activities share same predecessor

What does 'converging' mean in network diagrams?

Multiple activities are predecessors for one

A network diagram displays activities, time needed, and what else?

How activities relate to each other