Gantt Charts (AQA A-Level Further Maths): Flashcards

📚Flashcards
Gantt Charts
Sign up to keep revising.Create a free account to study more flashcards and track your progress.

Practise the cards

10 cards from this deck

Show

Another name for Gantt chart

Cascade chart

When Gantt charts are created

After critical path analysis

Formula: Earliest finish time

extEarlieststart+extDuration ext{Earliest start} + ext{Duration}

Formula: Latest start time

extLatestfinishextDuration ext{Latest finish} - ext{Duration}

Float definition

Flexibility in scheduling an activity

Formula for float

(extLatestfinishextEarlieststart)extDuration( ext{Latest finish} - ext{Earliest start}) - ext{Duration}

Critical activity characteristic

Has zero float

Critical path definition

Longest path determining minimum project duration

Non-critical activities have

Float greater than zero

Traditional Gantt layout feature

Early activities at bottom