Gantt Charts (AQA A-Level Further Maths): Quizzes

📚Quizzes
Gantt Charts
Sign up to keep practising.Create a free account to play more quizzes and track your progress.

Practise the questions

10 questions from this quiz

Show

What is another name for a Gantt chart?

Cascade chart

When are Gantt charts created in project planning?

After critical path analysis

In an activity network box, what appears in the top left position?

Earliest start time

How is earliest finish time calculated?

Earliest start time ++ Duration

What is the formula for latest start time?

Latest finish time - Duration

What is the formula for calculating float?

(Latest finish - Earliest start) - Duration

What defines a critical activity?

It has zero float

What does the critical path determine?

Minimum project duration

What is the first step in creating a Gantt chart?

Calculate timing information

Which activities should be plotted first on a Gantt chart?

Critical activities