What is float in project planning?
What is float in project planning?
Spare time available for an activity
Which formula calculates float for an activity?
Which formula calculates float for an activity?
(latest finish - earliest start) - duration
What defines a critical activity?
What defines a critical activity?
It has zero float
What does the critical path determine?
What does the critical path determine?
The minimum project duration
What does the critical path show through a network?
What does the critical path show through a network?
The longest route
To reduce project time with multiple critical paths, what must you do?
To reduce project time with multiple critical paths, what must you do?
Shorten activities on all paths at once
What does a forward pass calculate?
What does a forward pass calculate?
Earliest start times
How do you identify critical activities?
How do you identify critical activities?
Find activities with zero float
In network diagrams, what does the top left of an activity node show?
In network diagrams, what does the top left of an activity node show?
Earliest start time
Activity has days float but is delayed by days. What is the project delay?
Activity has days float but is delayed by days. What is the project delay?
days