Critical Paths (AQA A-Level Further Maths): Quizzes

📚Quizzes
Critical Paths
Sign up to keep practising.Create a free account to play more quizzes and track your progress.

Practise the questions

10 questions from this quiz

Show

What is float in project planning?

Spare time available for an activity

Which formula calculates float for an activity?

(latest finish - earliest start) - duration

What defines a critical activity?

It has zero float

What does the critical path determine?

The minimum project duration

What does the critical path show through a network?

The longest route

To reduce project time with multiple critical paths, what must you do?

Shorten activities on all paths at once

What does a forward pass calculate?

Earliest start times

How do you identify critical activities?

Find activities with zero float

In network diagrams, what does the top left of an activity node show?

Earliest start time

Activity CC has 22 days float but is delayed by 77 days. What is the project delay?

55 days