How much did the Morecambe coastal defence scheme cost between 1989 and 2018?

£30 million

What length of coastline is protected by the Morecambe and Heysham coastal defence scheme?

8.5 km

How much rock armour was installed along the Morecambe promenade and sea walls?

436,000 tonnes

Approximately how many breakwaters were built and how much limestone was used in total?

10 breakwaters, just under 1 million tonnes

How much did the sea wall replacement project cost between 2015 and 2018?

£11 million

How many homes and commercial properties does the new sea wall protect?

11,400 homes and 2,246 properties

What are the dimensions of each gabion cage used in the coastal defence scheme?

2m × 1m × 1m

What environmental designations does Morecambe Bay hold?

SSSI and SAC

How much sand was added to the beach as part of the beach nourishment programme?

89,000 tonnes

What does 'hold the line' mean as a coastal management strategy?

Maintain the current coastline position