Scheduling Problems (VCE SSCE General Mathematics): Flashcards
📚Flashcards
Practise the cards
10 cards from this deck
ShowHide
Practise the cards
10 cards from this deck
Scheduling in project management
Scheduling in project management
Process of allocating time to complete activities in a project
Duration of dummy activities
Duration of dummy activities
Always zero
Float time (slack time)
Float time (slack time)
Flexibility in starting activity without delaying whole project
Formula: Float time
Formula: Float time
EST (Earliest Starting Time)
EST (Earliest Starting Time)
Earliest time activity can begin after project start
EST rule for multiple predecessors
EST rule for multiple predecessors
Use the LARGEST value
LST (Latest Starting Time)
LST (Latest Starting Time)
Latest time activity can start without delaying project
LST rule for multiple following activities
LST rule for multiple following activities
Use the SMALLEST value
Critical activities
Critical activities
Activities with zero float time (EST = LST)
Critical path
Critical path
Path of all critical activities; longest path through network