10 cards from this deck
Process of allocating time to complete activities in a project
Always zero
Flexibility in starting activity without delaying whole project
Float=LST−EST\text{Float} = \text{LST} - \text{EST}Float=LST−EST
Earliest time activity can begin after project start
Use the LARGEST value
Latest time activity can start without delaying project
Use the SMALLEST value
Activities with zero float time (EST = LST)
Path of all critical activities; longest path through network
Show more