What is crashing in project management?

Reducing activity time to shorten project

Which activities should be crashed to reduce overall project completion time?

Only activities on the critical path

Why is crashing non-critical activities wasteful?

They have slack time; won't reduce total

When multiple critical activities can be crashed, which should you choose?

Lowest cost per time unit

Which is a method to crash an activity?

Hire additional workers

What happens to overall project time when you crash a non-critical activity?

No change in total project time

What should you check after crashing an activity?

If a new critical path emerges

Why is crashing activity B strategic if it appears in paths B-D-F-H and B-G-I?

It affects two paths simultaneously

Paths: A-C-E (27 days), A-F-H (19 days), B-D (28 days). What is the critical path?

B-D with 28 days

Activity F can crash by 3 days at 100 USD/day. What is the maximum cost to crash it fully?

300 USD