What is one key benefit of effective scheduling in project management?

Determining minimum time for the project

What information does a precedence table show?

Activities, durations, & predecessors

What is the duration of a dummy activity?

Always zero

What does float time represent?

Flexibility without delaying the project

What does an EST of 0 mean for an activity?

Activity can start when project begins

In forward scanning, which EST value is used when an activity has multiple predecessors?

The LARGEST EST value

In backward scanning with multiple following activities, which LST value is used?

The SMALLEST LST value

How is float time calculated for an activity?

Float=LSTEST\text{Float} = \text{LST} - \text{EST}

What defines a critical activity?

Zero float time

What happens if a critical activity is delayed?

The entire project is delayed